In the daily production process, the necessary preparations should be carried out before starting the spray dryer. First check the joints of the bearing and sealing parts of each device for looseness, the condition of the lubricating oil of each mechanical component and whether the water, wind and slurry valve ports are in the required position. Then turn on the power to check whether the voltage and the meter are normal. After the Zui, check the amount and concentration of the slurry in the slurry mixing tank. If there is any problem, it should be eliminated in time.
Then, the blower and the exhaust fan are sequentially turned on, and then the heating switch is turned on to start the temperature rise. When the outlet temperature reaches the set temperature (generally around 130 °C), start the material pump and dust removal system. When the pump pressure reaches 2 MPa, the spray gun is turned on to start granulation. After the equipment is running, the atomization and the working condition of the pump should be observed in time. If there is a gun blocking phenomenon, the nozzle should be cleaned or replaced immediately.
After the equipment is in normal operation, it should also be timed to receive materials, check the operation of each system regularly, record the process parameters, and pay attention to clean the vibration filter screen.
At the end of the granulation, the heating device should be shut down first to stop the gas engine operation. Then close the gun valve, replace the gun, unscrew the nozzle and rinse. When the inlet temperature is reduced below 100 °C, the operation of the blower and the blower can be stopped. Then clean the dry tower and the residual material in the precipitator, close the dust collector and the air hammer, and then turn off the main power supply to complete the production operation.
In case of emergency, the equipment must be shut down immediately. The blower and feed pump should be shut down first. If there is a sudden power outage, the gas engine should be pulled out to cool the tower naturally, then the drain valve is opened, the slurry in the slurry pipeline is drained, and the equipment is cleaned.
Then, the blower and the exhaust fan are sequentially turned on, and then the heating switch is turned on to start the temperature rise. When the outlet temperature reaches the set temperature (generally around 130 °C), start the material pump and dust removal system. When the pump pressure reaches 2 MPa, the spray gun is turned on to start granulation. After the equipment is running, the atomization and the working condition of the pump should be observed in time. If there is a gun blocking phenomenon, the nozzle should be cleaned or replaced immediately.
After the equipment is in normal operation, it should also be timed to receive materials, check the operation of each system regularly, record the process parameters, and pay attention to clean the vibration filter screen.
At the end of the granulation, the heating device should be shut down first to stop the gas engine operation. Then close the gun valve, replace the gun, unscrew the nozzle and rinse. When the inlet temperature is reduced below 100 °C, the operation of the blower and the blower can be stopped. Then clean the dry tower and the residual material in the precipitator, close the dust collector and the air hammer, and then turn off the main power supply to complete the production operation.
In case of emergency, the equipment must be shut down immediately. The blower and feed pump should be shut down first. If there is a sudden power outage, the gas engine should be pulled out to cool the tower naturally, then the drain valve is opened, the slurry in the slurry pipeline is drained, and the equipment is cleaned.
Pure Matcha Powder,Organic Matcha Pure Tea,Organic Matcha Pure Powder,Organic Matcha Pure Tea Powder
SHAOXING ROYAL TEA VILLAGE CO.,LTD , https://www.yccmatcha.com